I’m having a doubt on how to calculate max manpower required trade wise (ex: Mason,Carpenter etc ) per month after loading the labor resource below is the details im using
Calendar I am using : 10hours work for 7days
From resource usage Spread Sheet I’m getting
Mason for July 3420h
as per my understanding I am calculating as 3420/10=342 man-days
342/30 = 11.4 No of mason required for July
but some activity on July have loaded 20 mason per day so I’m getting doubt
Can any one please help me and Gide me how to calculate it.
Thanks in Advance
Aravind H P
Aravind,
Please stop posting the same question at regular intervals in order to bump yourself up to the top of the most recent list.
it is not fair on other posters, and quite annoiyng for regular readers. Which is why i have been deleting them.
Thanks,
Gary
(moderator)
Can i able to caluclate max no of manpower req per month is there any procedure.
(3420/10)30=11.4 is the daily average manpower required.however, you have the option to increase/decrease the manpower dependening on the availability of your resources as long as you could finish the job on time.