Manpower Caluclation

A
Aravind H P 👤 Member for 13 years 2 months

Hi Friends 

I’m having a doubt on how to calculate max manpower required trade wise (ex: Mason,Carpenter etc ) per month after loading the labor resource below is the details im using 

Calendar I am using : 10hours work for 7days 

From resource usage Spread Sheet I’m getting 

Mason for July 3420h 

as per my understanding I am calculating as    3420/10=342 man-days 

                                                             342/30 = 11.4 No of mason required for July 

 

but some activity on July  have loaded 20 mason per day so I’m getting doubt

Can any one please help me and Gide me how to calculate it. 

Thanks in Advance 

Aravind H P 

G
Gary Whitehead 👤 Member for 17 years 2 months

Aravind,

 

Please stop posting the same question at regular intervals in order to bump yourself up to the top of the most recent list.

 

it is not fair on other posters, and quite annoiyng for regular readers. Which is why i have been deleting them.

 

Thanks,

 

Gary

(moderator)

A
Aravind H P 👤 Member for 13 years 2 months

Can i able to caluclate max no of manpower req per month is there any procedure.

A
Ariel Malibiran 👤 Member for 17 years 3 months

(3420/10)30=11.4 is the daily average manpower required.however, you have the option to increase/decrease the manpower dependening on the availability of your resources as long as you could finish the job on time.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts