Hello Planners,
Is there any reason why a Project Activity Code would not indent in the Group & Sort dialog?
I can check the Indent checkbox of all the Activity Codes but one in my project, and I cannot see any reason why
Thanks for your help,
Alexandre
Hi Alexandre
Have you organised the activity codes structure similar to an WBS structure? So, with parents and childs. Orherwise i do not thick that it is possible.
Regards Johannes
do you use P 8.2 ?