I want to know your opinion about the workload´s difference in the monitoring of Planning type shutdown compared with EPC Planning.
How oft in minimum must a shutdown planning be updated ?
Thanks
Kamel
Hi Guys,
I want to know your opinion about the workload´s difference in the monitoring of Planning type shutdown compared with EPC Planning.
How oft in minimum must a shutdown planning be updated ?
Thanks
Kamel
Schedules for Shutdowns/Turnarounds/Outages should be updated at the end of every shift. Management should have updated progress reports and field supervisors should have updated shift (or "look ahead") schedules before the start of the next shift.