Exporting from P3 e/c to P3

A
Alan Callow 👤 Member for 21 years 5 months

Under Admin > Admin Preferences > Time periods > check the default time this may affect duration unless shown in hours

H
Henk van der Heide 👤 Member for 21 years 10 months

Imam,



I think you’ve a calender problem

Best way to find out: Check both durations in Hours.

It seems that 1 day is not always 8 hours work. (this can be the problem).



Regards



Henk