Project Finish becomes Early Finish After Scheduling.

L
Lee Johnson 👤 Member for 12 years 4 months

Ok, this is baffling me.

 

The schedule is a month behind where we should be, so i try to reflect this accurately within the programme, and this doesnt want to play ball, the Logic within these activities is sound.

 

Activity X - Submit Document A, Finish Milestone Date: 03rd March (*A*) - (Early Finish Date: 03 Feb)

FS With..........

Activity Y - Document A Review Period: 03rd March (*A*) to 28th March. (Early Start Date: 03 Feb - Early Finish : 28th Feb)

 

I have applied actual start date, and an expected finish. When i schedule the programme, even though i have an expected finish on Activity Y, it moves the dates back to Early Start / Early Finish, which is ignoring both its own logic (Starting before its predecessor) and the actual dates / expected finish dates.

 

So to clarify, when i F9 the programme, activity Y reverts to its initial Early dates, rather than its Actual Start date, and expected finish

 

 

I'm sure this is something very simple to fix.

G
Gary Whitehead 👤 Member for 17 years 2 months

1) What's your data date?

2) Do activites X or Y have any constrains on them? If so, what?

3) Any lag on the FS relationship between X and Y?

4) Also, under schedule options, can you confirm:

a) Is "use expected finish dates" ticked?

b) Retained logic, progress overide, or actual dates?

 

Cheers,



G

L
Lee Johnson 👤 Member for 12 years 4 months

Sorry Joe, no, i am using the start & finish columns, i have only brough in the Early Start & Early Finish columns to investigate the issue.

J
Joe Peck 👤 Member for 12 years 2 months

Hi Lee,

 

If I understand your issue correctly. In P6 you are using the Early Finish and Late Finish columns and they will always show the original early and late finish dates even after actualizing the schedule.  Try using the Start and Finish columns which will give you the correct actual start and finish dates.  Also make sure to move your data date later than the actual start and actual finish dates before you F9.  

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts