Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Ismael
Not really - they are both the same techniques but according to the American's TIA is for work in progress and SIA is for completed projects.
Best regards
Mike Testro
many thanks dear.
can we say that TIA is one of the approches of SIA ?
Hi Ismail
These are American titles.
In the definitions section of types of analysis prepared for the Virginia Department of Transport:
http://www.virginiadot.org/business/resources/const/0703_PrinciplesofSIA.pdf
The terms are defined as follows:
Modification Impact Analysis (U.S. Army Corps of Engineers) – a contemporaneous
schedule impact analysis technique in which at the time of modification, the
actual status of the job is determined, the schedule is updated, and the delay is
inserted to quantify singular impact
Time Impact Analysis – similar to the Modification Impact Analysis, a schedule impact
analysis technique that recreates the actual status of the job at the time of
modification, updates the schedule, inserts delays, and quantifies singular impact;
although retrospective in that it is done after the fact, it has a contemporaneous
orientation, not a hindsight perspective
Schedule Impact – the potential effect of a delay or change on a project schedule; may
be in the form of delay or change in project completion date, delay or change in
project sequence, or consumption of float
Schedule Impact Analysis (SIA) – the process of quantifying and apportioning the
effect of delay or change on the project schedule.