Budgeted Man Hour

V
VINOD KUMAR 👤 Member for 12 years 2 months

Sir,

 

Please help me in the following issue.

 

Already I have a baseline schedule but due to some material delay i had to revise my schedule . As per the new dates already updated the activities but the budgeted manhours was not moving to new dates in activity usage spreadsheet.

 

Thanks and regards

 

VInod Kumar

R
Ravi Katare 👤 Member for 11 years 10 months

Hi,

Run a GC;

If Planned start/finish is not equal to blank

Then Planned start/finish equal to Start/Finish.

What you have to do is replace planned start and planned finish with start and finish.

- Ravi

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Vinod,

What version of Primavera are you using? Did you right click on the Labor Units Section of the screen and select Spreadsheet Fields - Budgeted Labor Units?

If yes, you may want to Try Assigning baseline again=Go to Project>Assign Baseline and assign baseline again. If this does not correct the problem, I need to know if the Remaining Quantity and Budgeted quantity are the same in the Activity Usage Spreadsheet.

Thanks

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts