Resource Assignment Profile ( Total Quantity different in hour unit profile and Day unit profile )

Y
Yin Htwe 👤 Member for 12 years 6 months

Dear all,

Could you please advice me as I have been facing the problem in Primavera P6 Ver.8.2 as pre below.

In User Preference field, when I selected unit of time format as Hour, total quantity of manhour is tally with individual resource quantity. see below picture:

Image removed.

Image removed.

 

But When I selected unit of time format as Day, total quantity of Day does not tally with individual resource quantity. Please see below:

Image removed.

Image removed.

This is in same project and I just only selected unit format. total quantity is wrong.

Please advise me.

Thanks You;

Yin Htwe

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts