100% complete task problem in highlights

E
Engr Ewodge 👤 Member for 17 years 8 months

Hi group,

I have two concern that I want to ask for help;

1. I'm using MS project 2010, when I try choose to highlights all the tasks that are 100% complete, it's seem not all has been highlighted. There are still items that don't have highlights eventhough it's already mark as 100% complete. Is it flaw of MS Project? 

 

2. I'd like to ask if anyone can send me a copy of their ms project schedule loaded with resources. I'm in a construction consultancy firm and will likely to make a schedule for our upcoming project that has a resources. My email ad is [email protected] .

 

Thanks in advance for the help from this group.

More power.