please can anyone tell me how to enter the standard rates/ overtime costs in INR istead of $ dollars.?
Doubts in MSP -2007 & 2010
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
For Microsoft Project 2010, click on >File, >Options, >Display, then change the Currency to INR.
For more help on MS Project try this link.