% Complete Type

Dear, Everybody

I would like to know how to  change the " % complete type" is "physical" in all of activities.

I can't find way to use "fill up", "global change"..

Only way is to change each activities?

I need your help please.

 

 

X
Xenia Marami 👤 Member for 12 years 3 months

please can you explain how this field is opoen for completion , after it is revealed.

X
Xenia Marami 👤 Member for 12 years 3 months

please can you explain how this field is opoen for completion , after it is revealed.

X
Xenia Marami 👤 Member for 12 years 3 months

please can you explain how this field is opoen for completion , after it is revealed.

X
Xenia Marami 👤 Member for 12 years 3 months

please can you explain how this field is opoen for completion , after it is revealed.

X
Xenia Marami 👤 Member for 12 years 3 months

please can you explain how this field is opoen for completion , after it is revealed.

F
Feng Benjamin 👤 Member for 15 years 4 months

Hi,

You can do a fill down to achieve that.

Under "View", Choose "Columns" or click on the respective shortcut.

Open the column "Percent Complete Type" 

This will list the % Complete Type of all activities. You can then do a select and fill down.

Regards,

Benjamin

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts