Hi guys,
In P6 8.1, I found something strange with activity suspension; when I have updated the schedule with DD – 14/Feb/14 I found one activity to be suspended from 28/Feb/14 till 15/Mar/14.
After entering the suspension and resume dates, when I reschedule the activity moves and it shows that the remaining job to be performed only after 15/Mar/14 onwards. It doesn’t shows the work to be performed between data date and suspension date (14/Feb/14 ~ 28/Feb14).
This is affecting the resource distribution as well; have any of you experienced this? Advise if you have any suggestions to fix / get rid-off this problem.
Regards,
Abilash
Hi Abhi,
- If the suspend/resume functionality is used then the early start is set equal to the resume date, its design for work in this way only .
Hi Abilash / Mike,
I'm also experiencing the same issue! I checked all the settings and calendars and it still shows inactive period between the datadate and suspend date. Is yours resolved or you still have the problem? Please help / advise.
Regards, Nima
Hi Khaja,
There is no constraints or any driving relationships.
Br
Abilash
Please check if there any constraints imposed and activity relationships.
Hi Mike, Both calendars are active during 14/Feb/14 ` 28/Feb/14
Br,
Abilash
Hi Abilash
Check your calendars both on the task and resource allocations.
Best regards
Mike Testro