I have imported a schedule from MS Project to P6 v.7.0. I changed all of the activity types from "resource dependent" to "task dependent" and I changed the duration type from "fixed duration and units" to "fixed duration and units/time".
Now when I change an un-statused activity's original duration in P6, the remaining duration doesn't change. It appears that the link between OD and RD is turned off. Can someone tell me where I can reset this link? I can change each duration individually, but I'm curious as to why the RD doesn't change automatically.
unfortunately it does when u importing ms project into P6. i was wondering why my finish date doesnt move after i change the OD. End up, i find out the RD was different from OD eventho wtihout actual.
thanks..helpfull!
Hai Jay
Please check the below option
Project - Calaculation Tab - Link Budget and at acompletion for not started activities (Ticked)
Reset Remaining duartion & Units to Original (Enable)
Regards
Mani
DEar Jonathan,
There is no link between OD and RD unless the activitiy doesnt have any actual.
Regards,