Hi All,
Although i havent assigned any baseline to my schedule in bar chart i see baseline bars(project,primary or secondary) for actual activities seen attached picture
When i assign baseline i also see same bars[[wysiwyg_imageupload:1954:]]
Can anybody help me?
Mujdat,
That is how it is supposed to work. The manual states that if no baselines are assigned, then the Planned Start and Planned Finish dates in your current schedule will be used. It also states that once a baseline is saved and assigned, that the baseline schedule Planned Start and Planned Finish date will be used. If no status has been assigned since you assigned the baseline schedule, then those dates would be the same. Good luck!