Hi guys,
Im a newbie to this site..
I’m facing mentioning problem regarding Est. Weight in P6.7.
I got Two WBS in Which WBS 1 having a weight age of 6.2 & WBS 2 having a weigtage of 3.8.
That means if I completed my First WBS (2nd WBS’s activities not started) my overall percentage complete should be 62%.
I assigned proper weightage to all the activities , but it didn"t rolled up WBS summary performance % as well..
The problem is After finishing WBS 1 my Overall % shown as 57.89% instead of 62% .How to recover this issue.??
How to assign Est Weightage that overall % accurately roll up in WBS & Project level .???
Guys got any thoughts???
Thanks in advance
I do not use P6 but with a few formulas or global changes plus a script it shall be easy to do with your software.
http://www.youtube.com/watch?v=-hyTDRBK7v8
Same problem with me here.. haiss,..appreciate very much to anyone who can provide light on this particular P6 issue.. Thanks.
--------------
..............