Ms project - Actual cost column

Hi all planners,

I am using ms project-2007 for my scheduling works. I have created a schedule with work resource,cost resource and did save baseline. Now i want to change the values in actual cost column of cost resource based on the site progress but when i tried to do so, i got a problem. When i increase the value of actual cost more than that of baseline cost , the duration of the particular activity is also changing.

I increased the actual cost because of more wastage of materials in the particular activity. I didn't spend more manpower or duration.

Is there a way to enter the actual cost without disturbing the duration of the activity?

What am i missing?

Thanks in advance.

Regards,
Ram

B
Bala Murugan 👤 Member for 12 years 11 months

Evgeny,

              Yes, you are right. Thanks for your help...

 

Regards,

Bala

           

E
Evgeny Z. 👤 Member for 18 years 6 months

Bala,

I do not have project 2007, but I could not reproduce the behavior, described by you with MS Project 2010. The behavior I observed is as follows:

  • It is not possible to change actual cost until activity is 100% complete. The actual cost in this case is calculated by the formula Actual Cost=Activity Cost*%complete
  • After activity is 100% complete, one can change actual cost and it does not change activity duration

Regards.

Evgeny

B
Bala Murugan 👤 Member for 12 years 11 months

Hi kumar,

             The task is fixed work and effort driven. I have assigend work resource and cost resource. I didnt assign material resource. I entered the material value as a cost resource for the activity.

 

Thanks in advance,

 

Regards,

Bala

B
Bala Murugan 👤 Member for 12 years 11 months

Hi kumar,

             The task is fixed work and effort driven. I have assigend work resource and cost resource. I didnt assign material resource. I entered the material value as a cost resource for the activity.

 

Thanks in advance,

 

Regards,

Bala

K
Kumar Baiju 👤 Member for 15 years 5 months

Hi bala

 can you say what is the task type. Is it Fixed duration, fixed unit or Fixed work. another thing you have have to check that the activity is effort driven or not. Have you enter material resource.

 

Regards\\

K
Kumar Baiju 👤 Member for 15 years 5 months

Hi bala

 can you say what is the task type. Is it Fixed duration, fixed unit or Fixed work. another thing you have have to check that the activity is effort driven or not. Have you enter material resource.

 

Regards\\

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts