Very well put and applicable to all aspects of planning: even systems which appear complicated can be found to be simple if broken down into its consituent parts.
It never ceases to amaze me within my orginisation when I see porgrammes which inlcude only general first and second fix activitiies for mechanical and electrical installations (with no defenition of first and second fix either, which only adds the readers confusion). Especially when these activites can represent a third of the project value. I am curently pushing for my employer to cover the cost of a basic course in building MEP services for myself so that I might add more value to our project planning in these areas.
It would aid me greatly in the interim if you were able to forward a copy of the study you did for CIOB on to me. I have sent you a private meassage with my email in the event that you are able to.
MEP Planning is very easy if you follow the following basic principles.
You don't need to be an MEP Engineer - you only need to know that MEP works are one dimensional whereas structures are three dimensional.
There are three things in MEP - Liquid - Air - Power.
These are contained in Pipes - Ducts - Cables
These go in two directions within the structure - Horizontally - Vertically
Then there are the interface stages with the construction works - you can't fix any MEP until the structure is ready to accept it.
There is a piece of kit for each of the three things and these need a place in the structure for them to be fixed.
You need to plan for each piece of kit in an individual standalone system from start to finish - forget about 1st fix 2nd fix etc.
So AHU system 1 you will need - Horizontal Ducts under the soffit - vertical ducts in the risers - Fix Kit - Fix Outlets.
These will be installed as soon as the structure interface allows - there are no links between the stages but each stage links to a milestone - ready to connect - the milestone links FS to the Connect System task- which then links to another milestone ready for system test.
When all the Air systems are connected you are ready for the Wild Air test - which also needs Power.
It is a logical progression and you need to study the schematics to get it right.
Don't forget the test and commissioning which come in two stages - Static test for each level when ALL three systems are complete - allow at least 5 days for this - Overall test and commissioning when the structure is complete - allow at least 30 days for this.
Send me a private message with your email and I wil send you a method study that I prepared for the CIOB.l
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Mike,
Well explained, thanks for this info. Awaiting the work info.
Warm Regards,
Sunil.
Hi Mike,
I am new to this MEP Planning domain. It would be of great help if you could share me the details mentioned in your above reply to my mail ID.
[email protected]
Thanks In Advance,
Bhushan R S
Hi Mike,
I am new to this MEP Planning domain. It would be of great help if you could share me the details mentioned in your above reply to my mail ID.
[email protected]
Thanks In Advance,
Bhushan R S
hai mike testro
can u send the complete details of mep activites
Hi, brother ,can share ? [email protected]
Mike;
I have also sent you a msg with my email adress.It would be a great adition to my knowledge being a MEP Planner.
Regards
AB
Mike,
Very well put and applicable to all aspects of planning: even systems which appear complicated can be found to be simple if broken down into its consituent parts.
It never ceases to amaze me within my orginisation when I see porgrammes which inlcude only general first and second fix activitiies for mechanical and electrical installations (with no defenition of first and second fix either, which only adds the readers confusion). Especially when these activites can represent a third of the project value. I am curently pushing for my employer to cover the cost of a basic course in building MEP services for myself so that I might add more value to our project planning in these areas.
It would aid me greatly in the interim if you were able to forward a copy of the study you did for CIOB on to me. I have sent you a private meassage with my email in the event that you are able to.
Regards, Robert Hughes.
Yipee yeah, thanks Mike now I'm a planner
Hi Varma
MEP Planning is very easy if you follow the following basic principles.
You don't need to be an MEP Engineer - you only need to know that MEP works are one dimensional whereas structures are three dimensional.
There are three things in MEP - Liquid - Air - Power.
These are contained in Pipes - Ducts - Cables
These go in two directions within the structure - Horizontally - Vertically
Then there are the interface stages with the construction works - you can't fix any MEP until the structure is ready to accept it.
There is a piece of kit for each of the three things and these need a place in the structure for them to be fixed.
You need to plan for each piece of kit in an individual standalone system from start to finish - forget about 1st fix 2nd fix etc.
So AHU system 1 you will need - Horizontal Ducts under the soffit - vertical ducts in the risers - Fix Kit - Fix Outlets.
These will be installed as soon as the structure interface allows - there are no links between the stages but each stage links to a milestone - ready to connect - the milestone links FS to the Connect System task- which then links to another milestone ready for system test.
When all the Air systems are connected you are ready for the Wild Air test - which also needs Power.
It is a logical progression and you need to study the schematics to get it right.
Don't forget the test and commissioning which come in two stages - Static test for each level when ALL three systems are complete - allow at least 5 days for this - Overall test and commissioning when the structure is complete - allow at least 30 days for this.
Send me a private message with your email and I wil send you a method study that I prepared for the CIOB.l
I hope that helps.
Best regards
Mike Testro