Dear P6 experts,
Acttualy, our consultant dont get the same schedule % complete on his programme,
We took an example for one WBS level, activities have the same activity % complete, same expenses, but we don't get the same schedule % complete on the WBS Level?? My % complete is the same aas the manual calculation.
So the question is, Why his schedule % diffrent ? where is the problem?
Thank you all in advance.
Ahmed
Ahmed:
I reviewed how %Schedule and %Performance is calculated.
%Schedule at WBS level is related to your Baseline.
Manochehr wrote "Schedule %Complete at WBS level is calculated = PV/BAC "
PV is Planned Value Cost, related to your Baseline. If you don't have any Baseline assigned, it will take your current project dates as the Baseline. Maybe your subcontractor and you have <> Baselines.
%Performance is related EV/BAC (EV of your current project)
Review all these fields in both schedules
Regards,
Ross
Dears Ross/Manochehr,
As I know WBS WBS Schedule or Performance %=sum of activities %*Acti $/WBS $ Right?
As I said besfore, we have the same activity % complete, activities expenses, How can be the Summary % different?
Are there any preferences on P6 to change the Schedule/Performance % complete on the summary?
Rgedards,
Ahmed:
Sorry, I didn't answer you yesterday!
Check the following fields in your schedule and your subcontractor's:
Remember that Duration % Complete = (Original Duration – Remaining Duration) / (Original Duration)
Let me know,
Ross
Ahmed:
Sorry, I didn't answer you yesterday!
Check the following fields in your schedule and your subcontractor's:
Remember that Duration % Complete = (Original Duration – Remaining Duration) / (Original Duration)
Let me know,
Ross
Ahmed,
Schedule percent complete formula is different for Activities and WBS :
P6 use below formula for activity level:
Schedule % Complete = ( [Data Date] – [BaslineStart] ) / ( [Baseline Finish] – [Baseline Start] )
and below one for WBS level:
Dear. Rosalba,
First Thank you for your answer.
1.Actually, I sent him my layout, so it couldn't be layout problem.
2.Yes there is some differences on the calendar, it could be impact all this changes?
3.User Preferences: Could you please explain in more details this item?
Thank you in advance.
Regards.
Ajmed:
1) Review if you have the same Layout
2) If your consultant and you have the same calendar
3) User Preferences
Regards,
Ross