Leveling resources: "Activities that cannot be leveled". Why

Hi. I'm doing a feasability analysis for an early fase project. I'm trying to build different scenarios with respects to resources and time. I have around 100 activites. I've set Original Duration and Budgeted Labour units. When i use Shift+F9 i still get over-allocated resources. In the schedlog.txt - 4 activites are listed as "Activites that cannot be leveled". I see no reason why they cannot be leveled. Any clues?

 

Cheers

 

Haakon

H
Håkon Haukebøe 👤 Member for 13 years 8 months

Thank you guys. William, spot on! Rounding error led to marginal overallocation.

 

Cheers

 

Haakon

W
william chee 👤 Member for 12 years 5 months

make sure your budgeted units/time is lower or equal to max units/time.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

One potential reason: if the number of assigned resources exceeds the number of available resources.

I cannot imagine other reasons without looking at your project. If you will delete confidential information (usually costs) and will upload xer file at some file exchange site we may look at it to find the source of your problem.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts