Can any one please explain the effects of the : Baseline type and Unit of Measure tabs in the Admin Categories and which one is ideal for Proper planning output?
Thanks,will greatly appreciate.
Labor and non labor will be automatically in hours. Material type resources units shall be assigned accordingly.
@Raymund de Laza
thanks
In the unit of Measure,do we have to specifically chose the type of unit for each resource as per the Materials,labor and non labor?
I am a bit confused when it comesto this.
Godwin,
Baseline Type is just a labelling function when you add baselines. You can add customized label as you wish.
Unit of Measure is used to unitized Material Type resources.