Profile and Productivity

L
Luca Basile 👤 Member for 22 years 11 months

Hi

Could please any one help me in set up a profile for productivity?

 

Assumed we do have a TBM and the ground profile, could be possible to assign TBM productivity based on the ground, so that nay delay will be reflected in the re-scheduling?

 

If you do have any instruction on how to set this system would be extremly welcome

 

 

Cheers

Luca

X
xadlim B. 👤 Member for 14 years 4 months

Hi Guys,

Does anyone have any idea of the standard productivity rate of TBM particularly slurry type TBM?

Regards,

L
Luca Basile 👤 Member for 22 years 11 months

Hi

Tunnel Boring Machine

 

L

 

PS

I found the way, using a profile and task with Calculate optio set as Duration-profile

TILOS is a powerfull tools

 

 

L

L
Luca Basile 👤 Member for 22 years 11 months

Hi

Tunnel Boring Machine

 

L

 

PS

I found the way, using a profile and task with Calculate optio set as Duration-profile

TILOS is a powerfull tools

 

 

L

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts