Dear Professionals;
Please advise me if my understanding correct or not
if we use a unit percent complete as a percent complete type and entering the actual units after progressed schedule and use set calculation of performance percent complete from the activity percent complete, is that mean earned value = Actual value ??
Thank You a lot
yaser
Yaser,
P6 use below formula to calculate EV:
EV = Budget At Completion * Performance % Complete
in your case "performance percent complete" is equal to "unit percent complete" , so EV will ve calulated as BAC*Unit PC
and the answer to your question is no.
Regards,
Manochehr
Hello Yaset
if you want to use the actuals for calculation the progress (earned value) you should also be aware that your budget at completion is actual plus remaining ! if your budget at completion changes als your earned value changes
i use several global changes to set this right (after putting in the progress)
kind regards
Henk
Yasser,
Earned value will be based on the unit percentage complete. You have already selected
percentage complete type as unit percent complete..
Regards,
Sunil