P6 Resource Curves

The Enterprise menu lists a number of cost curves (bell shaped, front end loaded, back end loaded etc..)

How do I assign a cost curve to an activity or resource for a specific activity?  Any help is much appreciated.

 

Dave

Z
Zoltan Palffy 👤 Member for 16 years 11 months

curves are assigned to individual resources on individual activities. Assign a resource to an activity in the tab at the bottom then in the resource window rigth click choose Customize Activity Detail and expand the General tab and select curve.

now click in the curve window and choose the curve that you want to use 

S
SYED S SHAH 👤 Member for 10 years 4 months

I have made a revised schedule  in the middle of a project with actuals and remaining works in seperate WBS and costs and resources assigned to both. But when i look at the S curve is shows only one bar for all the costs and resource usage for actual works completed , the bar is at the month just before the data date . I want it to show distributed bars within the time period but unable to do so.... can you please advise 

 

thanks

S
SYED S SHAH 👤 Member for 10 years 4 months

I have made a revised schedule  in the middle of a project with actuals and remaining works in seperate WBS and costs and resources assigned to both. But when i look at the S curve is shows only one bar for all the costs and resource usage for actual works completed , the bar is at the month just before the data date . I want it to show distributed bars within the time period but unable to do so.... can you please advise 

 

thanks

M
mani M.R 👤 Member for 16 years 10 months

Hai Dave

 

Earlier when i used resource curve i faced the following issues when the activity status is in progress


1.Actual Cost is not getting updated.

2.Actual Unit is not Getting Updated.

3.Unit % Complete is not getting updated (based on Resource curve against Duration%).

4.Earned Value is showing zero (When we enable use resource curve option in WBS Earned value) .

5.At Completion Cost is not equal to budgeted total cost

6.At Completion unit is showing Irrerelevant data

 

Can you pls confirm whether you are also facing the same issue when the activity staus is in progress

 

Regards

Mani
 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts