Man Hours

I've completely tracked my project now i want to know my actual manhours how can i know that?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Amnar

What method did you use to allocate resources to your task bars?

If your modelling is based on duration = man hours / gang size then it is easy to create a graph of both planned v achieved man hours.

Best regards

Mike Testro