Percent complete, duration and activity type.

X
xadlim B. 👤 Member for 14 years 4 months

Hi guys,

Anybody here has experience of Tunnel Construction? What is the best percent complete type to use? How about the duration type as well as activity type?

Any input is highly appreciated.

 

Thank you.

R
Raymund de Laza 👤 Member for 16 years 6 months

Unit % must be used if you have the real qty of the Material Resource for every activity. I don't recommend Resource dependent as this will make your duration changing everytime Resources changes.

X
xadlim B. 👤 Member for 14 years 4 months

Raymund,

If the productivity rate is available, units % type works better? and it should be resource dependent activity type?

R
Raymund de Laza 👤 Member for 16 years 6 months

xadlim,

If you estimates the Duration of your activity based on linear meter of tunnel time then use the duration % type.

If productivity rate is not available then use Physical % as you estimated the duration based on assumption.

Fixed duration and Units is recommended.

Regards,

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts