Hi All,
There was a programme, I have seen, I think it was artemis (I speak under correction), where you could resource a single activity with several resources, and use off-sets. These different resources would be represented by different colours or patterns on a single bar. I think this is the type of thing Erik is envisaging.
Regards,
Philip
You can, of course use Powerproject and put as many milestones, all coded differently if you wish, on the same line.
David
Jaco,
do you use line of balance (we call them linear diagrams)?
Vladimir
Hi Erik
I would suggest you look at a line of Balance I think you mean more than one milestone per line
Cheers
You can use MSP for the same by customising the field and show on the same line.If it is in limited number you can do in P3 also.
You can apply filters and hide everything except milestones - it is simple.
You can move them to a special milestone phase and the phase bar will show all events. If you collapse this phase you will hide individual milestone bars.
I dont think that it is reasonable because you will hide also milestone descriptions.
Regards,