I have some critical activities (total float=0) are delayed by 27 days during updating, but it gives me only (-9) of total float
while it should be (-27)
for example it is to be finished according to BL at 1st of December 2013, according to update it delayed to be 27th of December 2013, and its baseline total float is zero, now it is giving me (-9) days of total float
the project finish date is constrained (must finish by)
this problem occured when i imported the update in another version of the baseline
any help is appreciated
Gary,
Please find my reply underlined
1) Float is measured in working days, not calendar days. Check the calendars of the critical activities to see how many working days are between 1st and 27th December. I guarantee you it won't be 27 sure i know it is calculated from working days, but i have a critical activity with float zero that have delayed with 21 working days according to my calendar, but it only gives negative 9 days of float
2) Check your must finish by constraint is 1st December already done
3) I do not underatand what you mean by "imported the update in another version of the baseline" -please explain. i have a revised version of the baseline due to some changes (shifting notice to proceed date by 3 calendar months), and it is not a change order, it is a whole new baseline, so i had to apply my actuals and updates on the new version
Mahmoud,
1) Float is measured in working days, not calendar days. Check the calendars of the critical activities to see how many working days are between 1st and 27th December. I guarantee you it won't be 27
2) Check your must finish by constraint is 1st December
3) I do not underatand what you mean by "imported the update in another version of the baseline" -please explain.