P6 Rel 6.2.1 Resource Assignments

I am assigning several resources to the same activity with budgeted quantities, progress % and remaining hours to complete.

I then need to view each of these resource assignments using the "resource usage profile" view so I can see the bars showing the work to complete.

The problem I have is that I cannot summarise the resources by activity, the activity will be visible but with all the resources listed as the header.

I know this can be done using "assignments" but this doesn't display the bars, only hours in a spreadsheet.

I have tried to filter out the individual resources by activity but so far unsuccessful.

R
Raymund de Laza 👤 Member for 16 years 6 months

You may create Activity Codes = Activity Name, Assign the Activity Codes to corresponding Activity then Use the Group and Sort to Organized by Activity Code.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts