Greetings all. I’m a new user of P6 rev7 and am having a challenge which I hope someone will help me with please. I would like to create a report to see resources man-hours, for a specific time period, of only the projects I have open. But, for some reason any report I create grabs all resources from any project within P6. I’m sure there is something simple I am missing. But for the life of me I can’t figure it out.
Regards,
Dear Mr. Daniel,
While creating the report through the 'Report Wizard' once you reach the 'Configure Selected Subject Areas' just create a new filter under the 'Filter' tab in order to show only the Manhours assigned to the open projects.
It should look like this:
Resource Type......................equals.....Labor
Assigned to Current Project....equals.....Yes
Best Regards,
Kaif Mohsin