All,
when I press f9 for re-scheduling, circle spins but no progress periods appear on which I do reschedule.
Where these progress periods hide during pressing F9.
Please Help.
Mike: Plz look at this. Its urgent
Regards,
Chris
All,
when I press f9 for re-scheduling, circle spins but no progress periods appear on which I do reschedule.
Where these progress periods hide during pressing F9.
Please Help.
Mike: Plz look at this. Its urgent
Regards,
Chris
Mike,
Thank you very much for sharing this valuable information. SOLVED
Regards,
Chris
Hi Chris
Here is an extract from the PP help section.
This should do it
Best regards
Mike T.
Some warning and notification prompts within Asta Powerproject include a check box that you can select if you do not want to be notified with the same information again. If you select this check box in a warning or notification prompt, the prompt will not appear the next time the same situation arises.
You can specify that if you ask not to be warned again when a prompt appears, this should apply permanently, or only to the current session. You can also restore all prompts that you have turned off in the past, so that all prompts are once more shown at the appropriate time.
To specify the way in which to deal with warning and notification prompts that give you the option not to be warned again:
Sorry Mike,
Here is the full detail of the issue
When I press F9, usually 'Reschedule Progress Period Warning' message comes on my screen showing
Straighten progess period : none
Progress entry period : Wk 23 ...
But unfortunarely once I clicked dont warn again so now this message is not coming on my screen. whats problem?
How to bring it back this Reschedule Warning message?
Please help.
Thank you
Hi Chris
What do you mean by Progress Periods?
F9 is not the only way to reschedule - I prefer using an Icon in the toolbar or use the ribbon option.
Best regards
Mike Testro