Dear All,

I want to have a graph between how much Perfomance% has been completed with respect to schedule %(of the whole Project).

A
Ammar Tauqeer 👤 Member for 12 years 8 months

I can only enter schedule % complete data upto current data date.But i want to have schedule % complete of the whole project before hand.

A
Ammar Tauqeer 👤 Member for 12 years 8 months

Thanks Mike.I want to show schedule % Complete(the problem is that i dont know how it is giving weightages to the activity and then to whole WBS) with Performance % complete Graph.(This is generated by the work i have done)

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ammar

This kind of data is best generated on an Excell Graph.

Copy the percent complete numbers into an excell sheet from both the actual and target and use the data to present a vertical bar graph for each section of work.

Keep the graph format for the next progress update.

Best regards

Mike Testro

A
Ammar Tauqeer 👤 Member for 12 years 8 months

Told them to do so but they want progress in terms of duration.

How much performance % is completed of Planned %

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts