Dear All,
I have imported a schedule from P3 to P6, all seem to be working fine untill I tried to update actuals.
the schedule early finish and early end dates seem the same. no effect on succesor activies .
how can i over come this problem
Dear All,
I have imported a schedule from P3 to P6, all seem to be working fine untill I tried to update actuals.
the schedule early finish and early end dates seem the same. no effect on succesor activies .
how can i over come this problem
I am almost afraid to ask but did you re-calculate the schedule? P6 is not like MS Project in that the default setting is to not automatically re-calculate the schedule after any change.
ronald ,
i imported a file from P3
any change to any activity is not affecting the rest of the project ..
i even changed the data date ...
nothing happened
Do you mean the Tool, "Apply Actuals" or "Update Progress" or are your referring to some other process?