Problems change effect

W
WAEL ELHAJJ 👤 Member for 18 years 3 months

Dear All, 

I have imported a schedule from P3 to P6, all seem to be working fine untill I tried to update actuals. 

the schedule early finish and early end dates seem the same. no effect on succesor activies . 

how can i over come this problem 

R
Ronald Winter 👤 Member for 23 years 5 months

I am almost afraid to ask but did you re-calculate the schedule?  P6 is not like MS Project in that the default setting is to not automatically re-calculate the schedule after any change.

W
WAEL ELHAJJ 👤 Member for 18 years 3 months

ronald ,

i imported a file from P3 

any change to any activity is not affecting the rest of the project .. 

i even changed the data date ... 

nothing happened 

R
Ronald Winter 👤 Member for 23 years 5 months

Do you mean the Tool, "Apply Actuals" or "Update Progress" or are your referring to some other process? 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts