Is there a way to totally blank out bars on the gantt chart over a certain time period?
Gantt Charts
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Martin,
I guess you are using P6, I suggests to set the period as non work and apply bar necking.
Regards,
Hi Martin
If all else fails try using typex.
Best regards
Mike Testro
what software?