Performance % Complete Vs Schedule % Complete from contractor point of view

hi all,

i'm new in planning field i'll be having a lot of questions soon and i hope all of you to help me , tnxx

my question is what is more helpful for the contractor in monitoring progress ( Performance % Complete Vs Schedule % Complete ) and why ????

J
Johannes Vandenberg 👤 Member for 16 years 4 months

Hi Haytham

You can measure and monitor progress in many different options. Since you are new in planning, i suggest that you start with the following.

  • Monitor progress in time. Check the Schedule Variance. This is the difference between the planned, the assigned baseline, and the actual progress.
  • Monitor progress in volume. Check the schedule % completion versus the performance % completion.  The schedule % completion is the planned progress and the performance is the actual achieved progress.

Regards Johannes

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts