Incorrect progress line

R
richu rose 👤 Member for 19 years 3 months

 don't know if any one of you have encountered but I am getting incorrect progress line, if planned & actual progress is 0% progress line shows to the left side of data line and sometimes if actual progress is more then planned still the progress line will be to the lft side of data line.

I am using P6V7

Regards,

Richu

J
Johannes Vandenberg 👤 Member for 16 years 4 months

Hi Richu

Note that the progress line is drawn on the basis of the assigned baseline. So, if the progress of an activity is less than the planned progress of the baseline schedule, the progress line shall be to the left side of the Data Date. Spot on the Data Date if the progress equal to the baseline date schedule. The same applies for activities ahead of schedule, the progress line shall be to the right.

Please also note that by reporting physical % completion type that not only the % needs to be entered but also the remaining duration.

Regards Johannes

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts