Planned Monthly and Weekly Progress

Greetings!

Hi Planners,

I extracted the Planned monthly and Weekly progress in P6, but the percentages does not match at every end of the month. Weekly percentage is beat higher compared to monthly. All settings have been applied accordingly,  e.g. unit of time, resource analysis, and timescale. Anybody can explain this problem.

 

Regards

Albert

M
Mike Testro 👤 Member for 20 years 6 months

Hi Albert

There are 12 months and 52 weeks in a year - so the weekly progress will overlap the months end and show a lerger result.

Best regards

Mike Testro