I just started recently in scheduling and I only have a basic skills in linking activities, please I need an advice to apply it in P6.
"Relatioships" or "sequencing" of activities are based on experience and logic. Suggestion please, where/how can I start learning or to have this knowledge?
any advice will be greatly appreciated.
Thank you in advance.
Many thanks for the reply:-)
Loop de Loop
Mike,
Make sure you wake up after reaching your destination, otherwise it would be a circular reference.
Rafael
Hi Rafael
After a heavy night I have often experienced driving to work while still asleep.
Best regards
Mike Testro
After getting dressed some people will drive to their jobs but you would be surprised how many women finish getting dressed while driving, so yu might have:
Female partially dressed [FS] Female Driving Car
[SS] Female finishing make-up while driving.
Definitivelly not as easy as FS relationship.
You might be over thinking this. PDM relationships (FS, SS, FF, SF) are just means to estalish the order in which work must be performed. Ex.:
Wake up [ FS -> ] Get out of bed [ FS -> ] Shower [ FS -> ] Brush teeth [ FS -> ] Get dressed
Have to finish one task before you can start the next one. Easy.