Hi All,
Can someone please help me?
I am trying to create a column titled Finish Variance CL14 and Finish Variance Last Period. I have successfully created these but don't know how to edit it or enter the formula to show me the variance/difference in the columns field.
Currently the fields are empty when I add the columns.
Please help!
Regards,
Patrick
Gary,
You are the best and a genius.
Thank you very much.
Regards,
Patrick
Patrick,
If your CL14 programme is saved as the Project Baseline, and your last period programme is saved as the Primary Baseline, then just insert the existing columns "Variance - BL Project Finish Date" and "Variance - BL1 Finish Date" (found in the durations group)
Then you can edit the column titles to mention CL14 and last period
No need to mess about with custom fields and formulaes.
Cheers,
G