Group Totals not using Project Default Calendar

J
John Cecil 👤 Member for 12 years 8 months

Hi

 

I am using Pimavea P6 Release 8.2 

 

I would like to know how to change the calendar used at the Group Totals. (Summarised to Project Level) 

Initially it uses Project Default Calendar as shown in the Calenda.....But on changing the default calendar it does not resummaise and does not give me resummarised date based on the default calendar.

(well actually Im working on a template from a previous poject and that has 7 days woking set as the project default calemdar,,, where as I want it in 6 days working+holidays at the project level....How can I do this??)

 

 

M
MOHAMED KYASUDEEN MOHAMED HANIFA 👤 Member for 14 years 3 months

1. Create a clender  with 6 working days and Holidays of Your Organization.

2. Then Assign the calender by bringing calender column and assigning your calender to all the activities.

A
A D 👤 Member for 19 years

The duration for the summary at WBS level is calculated in following two ways:

1. If all the activities lying under a WBS follow the same calendar then the duration at the summary level is calculated based upon that calendar only.

2. If the activities lying under a WBS have different calendars assigned to them then the duration at the summary level is calculated based upon the Project's Default calendar (the one that is assigned under the Defaults tab of the Project window)

Rgds,

Ravi

S
Shareef Abdul Azeez 👤 Member for 20 years 8 months

In addition to changing the default Calendar under Project - Calendars (Global)

 

You have to got to Enterprise -Projects- Defaults Tab ,,,,and change the Calendar .

 

 

 

Regsrds

Shareef

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts