Please need assistance in filtering baseline against my recent changes or vise versa:
If I want to filter out which activities has been recently changed or date moved against my latest BL just for double checking, which parameter/s I should use in my filter? The purpose is to know if there are some unwanted changes or moved dates not accordingly.
Thanks!
Many thanks GARY, it's working! And yes I use primavera:-)
Vic,
To see all activities that have a diferent start or end date to your BL1 use:
Variance -BL1 Project Start Date is not equal to 0
OR
Variance -BL1 Project Finish Date is not equal to 0
(Assuming you are using Primavera)
Cheers,