Hi people
Hope you can help, something that has just started happening in my version of P6 ver 7
I create a schedule, with logic links in etc when I hit F9 to schedlue all the tasks come back
to start on the data date therefore destroying the schedule any ideas????
Thanks
Steve
Thanks Kaif sorted the problem
Dear Steve,
If the tasks are already having the actual dates & percentages, then check for the 'Retained Logic' instead of 'Progress Override' options under the 'Options' button in the 'Schedule' tab.
Best Regards,
Kaif Mohsin