Custom field to show only PM name

Hi there,

I am using MSP 2010 prof. I have a file with over 90 projects. In the Gantt view I want to create a custom field named PM that only shows the assigned PM and not all the other assigned resources. Not all projects have a PM assigned. Any ideas on how to do this? The formula is doing my head in.
 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Paul

In the project start dialogue for each project there should be a field for Project Manager - or at least a field that can be adapted for that purpose.

There is no quick way but to enter the name of the project manager for each project.

The contents should then be displayed in your chart.

Best regards

Mike Testro