Approval of Baseline Schedule

K
Kaif Mohsin 👤 Member for 15 years 4 months

Recently, we received comments by the Client's Representative on the submitted 'Baseline Schedule'. One of the comment is to incorporate quantities in Primavera P6 and to provide the same along with production rates in 'Excel' format also.

My question is that is it mandatory to do provide the quantities & the production rates? What's the general practice in this regard, is it necessary to submitt this information all the time along with the Baseline Schedule?

Hoping to have some guidance on this issue from the Senior's out there. Thanks in advance.

Best Regards,

Kaif Mohsin

M
Mike Testro 👤 Member for 20 years 6 months

Hi Kaif

You do not have the quantities but you do have the prices.

Resource hours can be extracted from the net price by using a % labour cost divided by the hourly rate.

In this way you have closed the triangle of time / scope / money.

Best regards

Mike Testro

K
Kaif Mohsin 👤 Member for 15 years 4 months

Hello Mike,

Nice to hear from you again. I completely agree with you that the CR's request is vaid. Actually, our programme is loaded with 'Manpower Resources' and Cost. For Cost loading, the BOQ Cost was broken down to the required levels & details of the programme and assigned to the activities. 

One of the Contract Clause with respect to "Programme to be Furnished" says: "The programme shall include a histogram indicating the number of workmen and their respective trade and class which the Contractor and Contractor's Sub-Contractors proposed to employ on the site from week to week through the period of the construction of the work."

This what we did, but by bypassing the normal route of calculating manpower required based on quantities to be executed and the production rates. The Manpower resources were allocated to all the activities based on assumptions only, since we didn't have the quantities to work out the manpower required. Now, to be honest we don't have the quantities at all.

So, in this case what should be our response to such a comment from the CR?

Best Regards,

Kaif Mohsin

M
Mike Testro 👤 Member for 20 years 6 months

Hi Kaif

The C R is usually entitled to request any reasonable information from the contractor.

This request is normal for resource modelling data.

If your programme is not resource modelled and there is no requirement in the contract for it to be so then there is no basis for this data.

However if you get into a claim situation that requires info on low productivity you may regret not giving the data now.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts