Level of effort

Hi All.

Can anyone please help?

I am trying to creat a level of effort activity and have linked it as a SS with its predecessor and FF with its successor both with zero lag.

When I schedule, the level of effort activity only shows the start date as start and finish date with zero duration. I have tried putting the number of duration and finish date manually but it goes back to showing start date with zero duration and a negative float of 1 as soon as as I schedule.

Please help.

Cheers!

Patosaks

M
Mike Testro 👤 Member for 20 years 5 months

Hi Gary

Thanks for the information - why not just create a hammock?

Best regards

Mike Testro

G
Gary Whitehead 👤 Member for 17 years 2 months

Patrick:

 

the LOE Start date will be the earliest start date of all the SS predecessors of the LOE

the LOE finish date will be the latest finish date of all the FF predecessors of the LOE

 

Mike:

Patrick is using FF for a LOE (level of effort) activity. These are hamock-type activities in P6 typically used for spreading non-direct resources / prelims, and require FF to operate correctly

M
Mike Testro 👤 Member for 20 years 5 months

Hi Patrick

I can think of no situation in the construction process that requires a FF link.

Perhaps you can enlighten me why you need it.

Best regards

Mike Testro

P
Patrick Osakwe 👤 Member for 13 years 8 months

Thanks Garry.

In that case the LOE activity will assume the very 1st activity date as it's start date right?

cheers!

Patosaks

G
Gary Whitehead 👤 Member for 17 years 2 months

Patrick,

 

The FF relationship needs to be a predecessor instead of a successor.

LOEs should not have any successors.

 

Cheers,

 

G

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts