revised program - totally new program

A
Alaa Al haj 👤 Member for 18 years 7 months

 

I want to prepare revised program – but instead of using last update copy I want to prepare totally new program – of course the completed activities will be added as summary activities ( high level ) with 100% Status

 

Is this accepted contractually

G
Gary Whitehead 👤 Member for 17 years 2 months

Hi Alaa,

 

I agree with Mike. -Make sure you get agreement in advance that this is acceptable before starting down this path.

 

I cannot tell you if it is contractually acceptable since I don't know anything about your contract, but if I was acting on behalf of the client I would need a very good reason to let you do this, because it is not good practise:

1) Makes it easier to hide unjustifiable changes to the programme

2) Makes it very difficult to compare revised vs orginal programme (different AIDs & potentially WBS / descriptions for the same activity)

3) Makes the schedule of changes you should be including with the revised programme more complex than it needs to be

4) Rolling up completed activities to a high-level summary instantly makes the programme invalid for any meaningful forensic analysis of historical performance

 

Cheers,

G

M
Mike Testro 👤 Member for 20 years 5 months

Hi Alaa

This is not normal practice and you would need very good reasons to completely re-draw the remaining work in a new programme.

If I was the Engineer asked to approve such a new programme my immediate reaction would be that you were setting it up for an EoT claim.

So discuss things at the next meeting and get permission to re draw the programme before wasting your time.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts