Equivalent to Wbs summary in Ms project

Hi folks

is the there any equivalent to wbs summary (of primavera p6 ) in Ms Project 2007 ?

if yes , how to  to do it ?

Regards

Kamel

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Kamel,

there is no need to wbs sumamry in MS Project, as it is possible to assigne resources to summary tasks

Alexandre