daily target

Dear All

Due to project delay the client have prepare their own schedule as per the remaining work divided to duration of 14 weeks. therefore client come out the daily target however I have concern on the other activity if the activity 1 example cannot meet the daily target then other activity will also affected

is this the write method for planning. any advise

Regards
Ronron

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ronron

This is unusual - unles you have been asked to prepare a recovery schedule and you have failed to issue it.

Normally the Employer cannot instruct you to work to his programme - it could be constructive acceleration and cost the Employer a lot of money.

When you get your EoT in place the problem may go away.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts