Dear All
I want to share my views and your comments as well. We have a new project manager after a gap of more than one month. The project at status the moment
1- Progress percentage around 53%
2- 13 months behind the schedule
3- Project revised finish date is 30th June 2013 and its 22nd June 2013 today
4- Waiting for the response to our 4th EOT claim
5- ...
6- ...
7- ....
8- ...
9- ...
Off course the higher management must have briefed him the scope but, being a planner, I was thing that I would be the first one whom he would like to see on the site. Instead, he met the people in the order below
1- Construction manager
2- Project Engineers
3- Procurement officer
4- QS
5- QA/QC Manager
6- The Engineer
7- The Client’s Representative
8- Site engineers
9- Foremen (charge hands)
10- Me (the planner)
I was the last whom he met. After a short introduction he asked me to give him
1- A list of activities that we can execute, the activities we have all the resources available (manpower, material, logistics and petty cash)
2- Drawings Submittal Log, Material Submittal Log and Procurement log
by tomorrow morning. He didn’t ask me to give the contractual program (baseline / clause 14 program) or the working / recovery program.
I was very surprised as to why he didn’t ask for the program. But when I think over it I realized that he was right. We are 13 month behind contractual program, even the recovery program has also failed. The only thing we must concentrate on is what we can do / finis immediately or as soon as possible.
QUESTION:
1- Am I right
2- If not what should be his approach
3- If I am right, what are the more benefits of this approach
4- Your comments on his approach
5- What more he (or we or me) can do
Dear Mr. Devaux
Thank you very much for much a useful information and your continuous guidance. I think I will start this job by some where next week, and off course, will keep you informed to be myself on the track.
Cheers - Tanveer
Hi Vladimir
Thank you for you advice, sure I will download that
Tanveer,
if you will decide to buy Spider Project you will not need anything else. It does everything you may need for project and portfolio management. Demo version may be downloaded from www.spiderproject.com and you may ask any questions at Spider Project forum here.
Best Regards,
Vladimir
Hi, Tanveer.
First, please understand that these three software companies that compute drag are entirely independent of me, so I do not keep close track of what they cost or how they are supported. But the three are:
It is very important, before you compute drag, that you and your client arrive at an estimate of the value/cost of time: what is it worth for every week earlier or later that the project finishes. If your client is uncooperative in doing this, I recommend your using a clearly conservative estimate: be able to say "The very LEAST that it could be worth to pull in the schedule and avoid LDs (plus increased cost due to overhead!) is $X per day. Can we agree on that?"
Then:
Good luck, Tanveer, and please let me know how it goes.
Fraternally in project management,
Steve the Bajan
Dear Mr. Devaux
If you please tell me the software name you mentioned in your post. I am preparing presentation for my management to convince my management to buy EPPM-R8 & a Drag calculating software.
Tanveer
Dear Mr. Tastro
Thank you very much for your support and guidance. I have more then 30 year’s corporate experience in operation & maintenance and site execution, but in planning, well, when I am in my company I am very much confident but on this forum I think of myself a child. I really appreciate your support and guidance that really boost my moral and confidence up.
Cheers - Tanveer
Hi Tanveer.
Don't give up!
We all get despondent when faced with seemingly impossible problems and it is easy to lose heart.
At the moment you are too close to the problem to see any solution.
My advice is to step back - take a short break - relax and get some sleep.
Do something that you enjoy doing.
Then take another look at the situation with fresh eyes and the way through will be obvious.
You must support your new project manager with best planning practice and then maybe the inbuilt attitude to planners will change.
Good luck
Mike Testro
Dear Mr. Devaux
Thank you very much for your support and advice. I have read your articles and believe that I understand what Drag is and how this can help us saving yourself running out of time, but as many of other companies here in the ME my company also do not really believe in planning and hire the planners just to full fill the contractual requirements only. Sir, I do like finding solutions, but unfortunately I become exhausted & disheartened when the results are not in favor, I start thinking that I am nobody to do this. I cannot say whether it is due to lack of confidence or lack of knowledge. What I will try the way you mentioned coz this is the only way I can do this and I will also try my management to buy the software. Dear Sir, I told you my constraints so please don’t think that the solution you gave did not satisfy me.
I am also planning to appear in the PMP’s examination before the July 31st this year.
Cheers - Tanveer
Hi, Tanveer.
I'd guess your alternatives are these:
If none of the above solutions is satisfactory, then I'm afraid that what you are looking for is not an easy solution -- it's an effortless solution. And I'm afraid I don't have one of those.
Fraternally in project management,
Steve the Bajan
Dear Mr. Devaux
Thank you very much for useful adivse, I will certainly do that, my current schhedule has around 2600 activities and more then 200 in the critical path can you tel some easy way to calculate drag, I mean with using any drag calculation software coz my company is not interested in buying any of such software.
Cheera - Tanveer
Hi, Tanveer.
Whenever trying to recover schedule, your steps should be, in order:
1. Compute the drag of all current critical path activities, based on remaining durations.
2. Compute the likely drag cost (based on estimated LDs or forfeited early delivery incentives) of all current critical path activities, based on remaining durations.
3. Present the drag information to the project team, including subcontractors, show them where big drags are costing you the most time, and ask them to suggest schedule changes/alternatives to reduce drag.
4. When the critical path changes, compute the drags of the new CP activities.
5. Rinse and repeat until you have schedule that either meets your goals or is as compressed as you can get it. And if it is heavily compressed, remember that you are are likely to need anywhere for 10% or 40% additional time as schedule reserve.
If you wnat to know how to compute drag, try reading this article and this article.
Good luck.
Fraternally in project management,
Steve the Bajan
Dear Mr. Testro
Thank you very much for your expert advice, I really appreciate that.
Cheers - Tanveer
Hi Tanveer
You will notice that I have removed items 5 to 9 on your first list.
You should never put such confidential information in an open forum discussion - it is a complete breach of confidence that will prejudice your EoT claims.
You did not mention the project but you are the named planner so it is easily traced.
Your new manager is doing his best to get a grip on a hopeless situation - so you should support him as best you can.
The fact that he has put the planning function so low on his priorities is self explanatory.
Best regards
Mike Testro