I have this problem at work: I have my time schedule which is updated up to data date, now a new area is going to be added to project scope which the engineering and construction activities have been started 2 months before. now thay ask me to prepare a time schedule for this new work and incorporate it to my plan. please guide me in this regard how can I attach this new schedule to the project schedule(considering that some activitie in both are done or progressed) next how shoud I incorporate this change to the baseline?
Incorporating A new Time Schedule to your old one
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Javad,
it depends on the software that you use.
In Spider Project you just create the schedule for the new area and select Add project as new phase in the project pop-up menu. Then select your project for new area and that's all.
The same may be done with the baseline where you may add initial subproject schedule where actual data was not entered.
Hi Javad
Save the old programme in a new file and then just build up the new programme as if it was a sub-project.
Place the necessary logic to the old programme tasks and the enter progress.
Best regards
Mike Testro