Hi all,

I am presently faced with the following issue:

The supplier has submitted a MSP file to both me and another planner. However, when we open the file, both of us see different Project completion dates. Both our settings and file source being the same, how is this happening? Is there any way to resolve this?

 

Warmest Regards,

Benjamin

E
Evgeny Z. 👤 Member for 18 years 4 months

Feng,

I could think of the following (and I am not 100% sure):

Sometimes when you open MP project file it come out with the message about some conflict in the schedule and asks you what do do about this. Is it possible, that you answer this questions in different ways?

In any case, you probably need to troubleshoot it. I suggest that following:

May be supplier can also baseline schedule, before he sends it to both of you. Then,since baseline data is unlikley to change, once you received the schedule, you can check for differences between the baseline and the schedule (e.g. by checking the finish varience of tasks). By doing this you could find which tasks the difference comes from.

Finally, you can try to post message here:

http://answers.microsoft.com/en-us/office/forum/office_2010

or here:

http://www.msofficeforums.com/

Sorry fo rnot being too helphful

Regards.

Evgeny

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts